FULIN PLASTIC PLANT
Project: Fulin Plastic
Scope of works:
Upgrading the systems of Power, Drives, Control of production lines: provision, installation, testing and commissioning the SWG, MCC, motors, cable raceway, cables
Schedule:
2 weeks for each lines, working continuously 3 shifts per day
The Engineers, Workers of TLC have closely cooperated with Experts, Engineers of Fulin Plastic, worked hard to complete the works of provision, installation, testing and commissioning all equipment, materials and set production lines in operation successfully in accordance with desired schedules.
Fulin Plastic Plant

Tool Box Meeting-TBM prior start working

Fabricating steel supports

Terminating cables for Power Distribution Boards

Installing at site

Pulling cables at site

Terminating cables in Motor Control Center-MCC

A break at site