THE COGEN 30MW PROJECT IN ACCELERATION STAGE
After the Covid 19 4th booming in South of Vietnam, TLC accelerating the Co-Generation 30MW system for Kraft Paper Plant project. We paid much effort in installation works in order to hand over to Pre-commissioning stage.
The scope of work is installation services for electrification systems (Power supply-Drives-Control and Instrumentation).
The details are as below:
- Transformer
- MV, LV SWGs
- LV MCC
- Cable raceway: ladder, tray, conduits
- MV-LV-C&I Cabling works
- Cable termination
- Instrumentation tube
- Instrumentation systems.
- Supporting T&C works.