KRAFT PAPER PROJECT 2020

The year of 2020-during Covid19 time, TLC completed the Kraft Paper Plant project.

The scope of work is installation services for electrification systems (Power supply-Drives-Control and Instrument).

Project duration is 4-6 months, TLC mobilized 150 men in peak time.

The details are as below:

  • Transformer: 14 sets
  • MV, LV SWGs: 60 sets
  • LV MCC: 80 sets
  • Cable raceway: ladder, tray, conduits
  • MV-LV-C&I Cabling works: 500,000m
  • Cable termination: 10,000 ends
  • Instrumentation tube: 5,000m
  • Pneumatic tube: 20,000m
  • Supporting T&C works.

 